Contractual terms : Delivery of Materials demolition docks before reconstruction of the train station. The flow rate requested 50 To/h and the grain size : 0/150 mm
Problématic : Evacuation of overburden removal from the tunnel access to the docks and stockpiling outside with 9 m in height. The conveyors must be placed in a gallery under railway and has to be moved for maintening an access to the docks. Duration of dockyard controlled and limited.
Our solution : Location of two conveyors belt MANUBLOC E.A 25 m x 500 movable, wheel-mounted portable. Operating of well-being to a convoyer stockpiling MANUBLOC E.A 18 m x 500 movable and reversal. Height stacking : 9 meter.
· Preparation deadline : 3 weeks
· Term of the facility : 2 months
· Site place : France